Predecessors

Modified on Fri, 15 Nov, 2024 at 2:22 PM


Cora allows the user to create different types of links between tasks in the Gantt chart.



  • Click ADD



The most common type of link is a Finish to Start (FS) link. 


Cora supports all the common predecessors:


  • FS Finish-to-Start
  • SS Start-to-Start
  • FF Finish-to-Finish
  • SF Start-to-Finish


Elapsed time is used when the lag duration includes non-working days.


Set the predecessor to make the start date of a task dependent on the end date of one or more tasks. 


You can also do this by dragging one task onto another in the Gantt.


The predecessors of a particular task can be viewed in the predecessor column and can also be edited and changed there.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article