Scheduling Analysis - Driving Task

Modified on Thu, 21 Aug at 3:26 PM

 

Introducing additional columns and functionality for improved project schedule analysis. 

  1. Full Screen Mode
     The user will have the option to hide the project summary and left-side Cora panel, providing users with a full-screen view to focus on detailed schedule analysis.
  2. Driving Indicator
     A new column will be added under the Predecessor tab in task details to show a checkbox indicating whether a predecessor task directly influences the start or end date of the current task.
  3. Go To Task Capability
     Users will be able to click on a task in the Predecessor tab, which will then navigate to and highlight that specific task within the schedule for easier tracking and review.
  4. Critical Indicator
     A new column will display under the Predecessor tab to indicate whether a task is part of the critical path, indicating that it impacts the overall project completion date and has zero total float.
  5. Total Float
     A new column will calculate and display the total float for each task within the Predecessor tab, allowing users to see how much scheduling flexibility exists for each task.
  6. Go To Task Capability
     Users will be able to click on a task in the Predecessor tab, which will then navigate to and highlight that specific task within the schedule for easier tracking and review.

Value

These updates improve navigation, tracking, and decision-making within project schedules, ensuring better visibility, efficiency, and control over project timelines.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article