Adjusting the 'Hours Per Day' Setting for a Project

Modified on Thu, 3 Jul at 11:52 AM

The 'Hours Per Day' setting limits the number of work hours that can be assigned to a resource per day on a project. By default, this is commonly set to 8 hours.


If a Resource Manager needs to allocate more hours per day to a resource, they can update this setting within the project.


How to update the 'Hours Per Day' setting

  • Navigate to the project.
  • Go to the ‘Properties’ section.
  • Locate the ‘Hours Per Day’ field.
  • Update the value to the desired number of hours.
  • Save your changes.


Note: Increasing the hours per day will allow more work to be scheduled for each resource per day, so adjust carefully based on resource availability and workload.



Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article