Work in Weeks (WinW)

Modified on Thu, 21 Aug at 3:57 PM

 

Resource Demand skill demand request has been enhanced to enabled project managers and resourcing teams to request and fill demand by Weeks. Working in Weeks works when Fiscal Calendars are enabled.

 

1 – Prerequisite

Under ADMINISTRATION | System | Project, the Enable Fiscal Calendar checkbox needs to be selected. Fiscal Calendar data is displayed under ADMINISTRATION | Business Planning.

 

2 – Determining the 1st day of the week

The system will look at the Fiscal Calendar and get the day from the 1st day from a full fiscal month and display the day as read only on ADMINISTRATION | System | General.

      

 

3 – Project Properties

With Fiscal Calendars enabled the PM can set the Resource Demand Period set to Weeks on the project properties. Once Skill demand is pushed to Resource Demand this field will become read only. To reset the data from the resource allocation screen needs to be cleared out.

A screen shot of a computer 
AI-generated content may be incorrect.

 

 

4 – Push to Resource Demand

When set to Weeks on clicking the Star icon on the Gantt, the prompt will display all weeks for the duration of the project. The current week will be highlighted by default.

A screenshot of a computer 
AI-generated content may be incorrect.

 

5 – Linear Skill Demand Requests

On the Gantt there are not changes to requesting skills, but on the resource, allocation screen the data will be broken down into the weekly periods according to the fiscal calendar and start day of the week.

Task created with 36 Days duration.A screenshot of a phone 
AI-generated content may be incorrect.

Skill demand added for the 36 days.

Resource Allocation screen shows the breakdown. Week of Jan 01 – Jan 03 has 2 working days.

 

 

On adding a named user, the periods are broken down by weekly period.

A screenshot of a computer 
AI-generated content may be incorrect.

 

6 – Distribution Curves

On the Gantt, if using Custom distribution curves, the data is split evenly across the number of weeks, with Edit option.

On pushing to Resource Demand, the data is split as per the periods set on the Gantt.

 

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article