Admin - Task Types

Modified on Fri, 25 Sep at 1:14 PM

Scheduling: Task Types

In project management—especially within Earned Value Management Systems (EVMS)—task types define how work is categorized, planned, and measured. Each plays a distinct role in managing scope, schedule, and cost.

Cora Task Types & Definitions

Task Type

Definition

Control Account (CA)

The control account is the intersection of one WBS element and one organizational structure element representing a specific portion of program scope assigned to an individual manager. The control account is the minimum level where technical, schedule, and cost responsibility exists.

Detailed Task (TSK)

Lowest level tasks in a Gantt schedule.

Hammock (HAM)

A hammock activity is a grouping mechanism that summarizes or aggregates multiple related activities under a single, high-level task. The purpose of a hammock activity is to carry overhead costs and resources during a portion of the project. Like a level of effort task, it’s a way to apportion overheads without having to split them between the other activities or to summarize time required as a result of several tasks. 

Milestone (MS)

A zero-duration schedule event or point in time that is measurable but does not consume time or resources.

Planning Package (PP)

A PP is a holding account (within a control account) for budget for future work that is not yet practicable to plan at the work package level. The PP budget is time-phased in accordance with known schedule requirements (due dates) for resource planning and plans are refined as detail requirements become clearer and time to begin work draws nearer. 

Schedule Margin (SM)

A technique for improving schedule accuracy by modeling the anticipated impact of schedule risk in the schedule. Schedule margin activities are established and managed as a margin of time in the schedule to offset unforeseen issues during project execution.

Schedule Visibility Task (SVT)

A schedule activity that is not resource loaded and represents effort that is not part of the budgeted project scope, but is necessary to complete a logical sequence of activities and properly time-phase downstream project effort. 

Summary (SUM)

A higher-level task that represents a group of subtasks or phases within a project. It's essentially a container for other, more detailed tasks.

Summary Level Planning Package (SLPP)

Used to establish high level holding accounts for budget that is identified to some work scope, but which is not ready to be detail planned so, has not yet been allocated to Control Accounts (CAs).

Work Package (WP)

A WP is a task/activity or grouping of work under a Control Account. A WP is the point at which work is planned, progress is measured, and earned value is computed.


content.emoticon.pin Toggles

Feature Toggle(s)

Permanent Toggle(s)

 NA

 KanbanBoard


?️ Configuration (Admin)

  • Navigate to:

    • Administration > System > Task Configuration

  • Enable Task Types:

    • Check the box for Enable Task Types.

  • Milestone Duration Setting:

    • If not using durations on the Milestone task type, disable the Allow Milestone Duration option (enabled by default).

      image-20250703-162342.png
  • Task Type Management:

    • Go to Task Types & Cora’s default task types will be prepopulated.

    • Admins can edit existing task types or add new ones to meet customer-specific requirements.

  • Additional Options:

    • Task types can be flagged as milestones or set with resourcing restrictions as needed.

    • Warning messaged when Task Types and Milestone Deliverables are out of synced can be also customized here.

image-20250703-162431.png

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article